[Completed] [Hazard notice][Monash] Data Center Routers upgrade on 12th September 2020

Monash Network team is planning to upgrade firmware in Data Center Routers to resolve security vulnerabilities and fix bugs.


Scheduled Start: Saturday 12/09/2020 07:00 

Scheduled End : Saturday 12/09/2020 20:00 


Affected availability zones: 

  • monash-01
  • monash-02
  • monash-03


Affected Services:

  • WAF / imperva traffic, WAF bypass vlans
  • Nameserver
  • All Data Center traffic


Impact:

There is no network outage anticipated, however there will be a period of 20 minutes where redundant uplinks to switch infrastructure will be offline. Users may notice several minor (1-2 seconds) interruptions during the day while communicating between availability zones, Monash corporate network and external network.


Monash Research Cloud

(On behalf of Monash Network Team)

Login or Signup to post a comment