[Complete][Hazard][monash-02] Storage cluster upgrades week of 14/8/2017
Posted
about 7 years ago
by Rafael Lopez
R
Rafael Lopez
Overview
Starting from today Monday 14/8/2017, the storage cluster servers underpinning Cinder volumes in the monash-02 availability zone of the Research Cloud will be upgraded (general updates and kernel patching). These will continue until all servers have been completed with an estimated total duration of 3-4 days.
Impact
We do not expect any significant impact as all cluster operations continue as we upgrade servers one at a time.
Action
If you experience any ongoing IO issues please report them to support.
Overview
Starting from today Monday 14/8/2017, the storage cluster servers underpinning Cinder volumes in the monash-02 availability zone of the Research Cloud will be upgraded (general updates and kernel patching). These will continue until all servers have been completed with an estimated total duration of 3-4 days.
Impact
We do not expect any significant impact as all cluster operations continue as we upgrade servers one at a time.
Action
If you experience any ongoing IO issues please report them to support.
Update
Upgrades are continuing this week (21/8/2017).
Completed
This activity was completed 25/8/2017.
0 Votes
0 Comments
Login or Sign up to post a comment